Step by Step Guide Veeam B&R 9 Update 2 Installation!

Veeam released Veeam B&R 9 Update 2, which contains some significant improvements such as NetApp Data ONTAP 8.3.2 support and VMware VSAN 6.2 support. You can find more information about the release here.

This article provides a step by step guide for an update from Veeam Backup & Replication 9 (version 9.0.0.902 or 9.0.0.1491) to Veeam B&R 9 Update 2 (version 9.0.0.1715).

Veeam B&R 9 Update 2

For more security:

The first step is to realize a configuration backup of Veeam server (“Configuration Backup” menu on the screenshot below) and if the Veeam Backup Server is deployed on a Virtual Machine, execute a backup of this VM with Veeam B&R.

Veeam Menu
When the backup is done, you can close Veeam software and restart the Windows server to clear any locks on the Veeam services (reboot). Basically I recommend you to stop properly the 6 or 7 Veeam services before upgrading (services.msc).

Running the Installer:

You have to run the installation file “veeam_backup_9.0.0.1715.update2_setup.exe”.

Veeam now preparing the wizard.

Installation Wizard:

Once installation wizard is launched, click on “Next” button.

Veeam B&R 9 Update 2 Wizard
Then Veeam will prompt to install the update 2, click “Install”.

Veeam B&R 9 Update 2 Wizard
The update took about few seconds to complete.

Veeam B&R 9 Update 2 Wizard
Veeam B&R 9 Update 2 Wizard
Once the upgrade completed, a prompt appeared to finalize the installation. Click on “Finish” button.

Veeam B&R 9 Update 2 Wizard
Post Reboot:

When the upgradre is done, I recommend you to restart properly the Windows server (reboot) and start the Veeam services.

Upon opening Veeam B&R, a prompt will appear to update the components (especially the Veeam Backup Server and the Proxy Server). Click on “Next” button.

Veeam B&R 9 Update 2 Wizard
Finally, when all components have been upgraded, you can click on “Finish” button.

Veeam B&R 9 Update 2 Wizard
You can check the version in “About” tab (“Help” menu) : 9.0.0.1715.

Veeam B&R 9 does not require new job creation or any architecture changes for your existing backups and replication to work. If there are dedicated Veeam proxy servers in the environment, now is a good time to upgrade those servers, otherwise, Veeam is now ready to use.

As a result of on-going R&D effort and in response to customer feedback, Update 2 includes over 300 enhancements and bug fixes, the most significant of which are listed here.

You can learn more about Veeam Backup & Replication 9.5 here.

 

 

Please follow and like us:
Advertisement

9 pings

Skip to comment form

  1. […] Continue reading » […]

  2. […] Need to deploy Veeam B&R 9 Update2? Follow this guide! […]

  3. […] Need to deploy Veeam B&R 9 Update2? Follow this guide! […]

  4. […] proxy and repository are working. To install Veeam B&R 9 Update 2 you can follow this post: Step by Step Guide Veeam B&R 9 Update 2 Installation! This article provides a step by step guide for an update from Veeam Backup & Replication 9 […]

  5. […] Need to deploy Veeam B&R 9 Update2? Follow this guide! […]

  6. […] Need to deploy Veeam B&R 9 Update2? Follow this guide! […]

  7. […] Need to deploy Veeam B&R 9 Update2? Follow this guide! […]

  8. […] Need to deploy Veeam B&R 9 Update2? Follow this guide! […]

  9. […] Need to deploy Veeam B&R 9 Update2? Follow this guide! […]

Leave a Reply

error

Enjoy this blog? Please spread the word :)